Logan County Board
Zoning Committee Reviews Data Center Ordinance Recommendations

[October 07, 2026]  The Zoning and Economic Development Committee of the larger Logan County Board met for their monthly meeting on Monday, October 5th. This meeting was held in the first floor courtroom of the Logan County Courthouse immediately following the Transportation Committee meeting. Four of the six committee members were present, including Chairman Gil Turner, Vice Chairman Kathy Schmidt, Hannah Fitzpatrick, and Joseph Kuhlman. Bob Sanders and Keenan Leesman were not present.

The agenda for this meeting only had one item on it, that being a review and discussion of the draft data center ordinance. Turner led the committee through a discussion on each part, with Zoning Officer Al Green providing many clarifications and overviews when needed. Springfield law firm Brown, Hay, & Stephens provided the recommendations that the committee discussed.

The first issue discussed was the setback, or how far a data center would have to be located from the nearest property. Leesman had a written recommendation of 500 feet, with room to be farther on a per case basis during the application and planning stages. BH&S recommended setting the minimum at 750 feet, which is what the committee went with.

The Emergency Management Plan was next. Green explained the argument here was that since data centers do not change “significantly” over time, rather than submitting a new plan each year, the data center would only have to submit a new one when changes are made. He argued this would make record keeping easier on the county side, and the committee agreed.

The next few were short discussions. The committee agreed that the data center should not be able to sell power they generate on their property if they have on-site generation. They determined that any data center would be required to have a closed loop cooling system to cut down on water consumption. They also added language about the data center having to follow state and federal guidelines on reporting.

Next, the committee discussed and agreed to some limits on the data center’s building permit. Any data center would not be allowed to get a separate building permit and build onto their existing structure as a way to bypass regulations on the original structure.

A decommissioning plan was briefly discussed. It was determined that this part would be worked on later. The committee also agreed to a clause that no public official would be allowed to enter into a non-disclosure agreement (NDA) with any data center company building in the county.

Chemical discharges and noise were next. The committee agreed that, in addition to reporting chemical discharges at the federal and state level, data centers would be responsible for reporting them to the county as well. With noise, the committee had to set it at 55 decibels during the day and 45 decibels at night. Green explained that they are not allowed to make noise restrictions that are more strict than the state or federal limits.

Next, the committee discussed a height limit, with 50 feet being the recommendation from BH&S. The eave of the building would be limited to 35 feet, with 50 feet being a hard limit for everything. Green agreed with this recommendation after his dealings with Hut 8. Initially, Green said, Hut 8 said nothing would be over 30 feet. After some time, however, they came back and said they would need 40 feet. The committee agreed to this.

Fuel containment and tile drainage were discussed next. The fuel containment is controlled by the state fire marshal, according to Green. As for tile drainage, the committee agreed with BH&S’ recommendation of having the data center company be responsible for any drainage tile damage that is tied back to the company.

Anti-phasing was after. Green explained that the data center cannot transfer ownership of parts of their property to avoid parts of the ordinance.

Next, the committee discussed soil restoration during decommissioning. Green stated that, if the M1/M2 zoning restrictions are put in place (meaning data centers can only be built on the land zoned M1 or M2 industrial), this would not be a problem. Green said he did not see there being a situation where, after the data center left, the land was rezoned agricultural. He said this would cost a lot of time and money.

[to top of second column]

 

Turner said he was against this, as he did not see the farm land being able to be restored. Schmidt argued that these companies should still be held accountable to try. The committee decided to leave the soil restoration clause alone.

Low frequency noise was next. It was determined that the United States does not have standards for these types of sounds. Green said that there are standards in Europe, but that adopting those would be difficult to enforce. The committee determined that requiring a study on these kinds of noises would be beneficial and left that language in the ordinance.

Two items regarding generators were then discussed. First, if replacing generators, the data center would need to replace them with better models. When storing those generators, they would need to be in structures that limit sound.

Next was insurance. Green said that the BH&S recommendation was to require them to provide insurance of no less than $5 million. In areas where insurance is not available, the company would provide letters of credit or bonds in the maximum amount.

There was a clause on supporting facilities. Any supporting facilities to the data center, such as a solar field, would be subject to the data center ordinance as well. BH&S also recommended against adding a clause that would require the company to disclose how much they have paid utility companies for upgrades to power infrastructure. In addition to stating that the county is not entitled to this information, much of it is also likely to be confidential. The committee agreed with this recommendation.

A discussion was had next on penalties for failure to file an annual report. The recommendation stated it would be $250-$500 per week. Schmidt asked if that amount could be made higher, and Green informed her that it could be pretty much whatever they want. Green’s work for making a fee schedule for wind and solar projects was discussed. The committee then decided to match the wind and solar fee penalties.

The next two items were the requirement of a study on the use of non-potable water and landscape buffers. With the landscape, the trees around the data center would be required to be a certain height, but that height was not discussed.

The final item discussed was determining whether or not the county would require data centers to be built on land zoned M1 or M2 industrial. Green shared that a comprehensive plan for the county is being worked on. The idea would be to direct potential data centers to land that is already zoned M1 or M2 and not to have them rezone agricultural land. Green did say that rezoning would have to be allowed if the county adopted this item.

This was the only item the committee voted on, and it was a tie vote on adding it. That being the case, it failed. It was revealed that the Regional Planning Commission (RPC) or the Zoning Board of Appeals (ZBA) could add this item back if they wanted to.

Once all of the recommendations were worked through, Green said the next steps would be putting them together in an actual draft ordinance and sending them on to RPC and ZBA for review.

Green then gave his Zoning Officer’s report. He said that the Pike Creek wind farm would be paying their tower fees shortly in the amount of $610,000. Additionally, Green shared that he got word that Pike Creek might be looking for more variances, something they said last month they would not do again. While last time, this was to keep the project alive, according to Green, this time is to save money.

Public comments were last. Many of the comments were questions regarding the ordinance that was just discussed. Allison Isley asked about the county getting an enforcement officer to help enforce this ordinance once it was put in place. Lisa Edwards recommended increasing the setback to a minimum of 1,000 feet. Several others made comments against data centers. After public comments, the meeting was adjourned.

[Matt Boutcher]
 

Back to top