[October 12, 2026]  The Finance Committee of the larger Logan County Board met for a special meeting on Thursday, October 8th. This meeting was held to discuss the fiscal year 2027 (FY27) budget. The meeting started at exactly 6:30 p.m. and was held in the first-floor courtroom of the Logan County Courthouse. Chairman Joseph Kuhlman, Vice Chairman Kathy Schmidt, Dale Nelson, Keenan Leesman, Lance Conahan, and Andrea Hinton were all in attendance.

Justin Greeley and Dustin Harmon with Bellwether were present to help the committee go through the budget. Nelson started by asking about a new draft budget that they had all received that day, stating he was not sure they were going to be able to proceed with the meeting since no one had had a chance to review it at such late notice. He also noted that there was a difference of about $200,000 in the old and new drafts.

Greeley shared that the majority of the change came from an increase of the property tax levy. He shared that no amounts were changed with any departments. Greeley continued, stating that the budget is currently at a $322,000 deficit. He said that this was due to a decrease in revenue. State income tax decreased, and the Circuit Clerk fines and fees went down, among other areas.

Harmon continued, saying that passing a deficit budget is not something that is not sustainable. Harmon also stated that, due to the state increasing the minimum wage over the last five years, that has increased labor costs for the county. He gave an example, stating that the growth in labor expenses from the Sheriff’s Department alone exceeded the county’s growth revenue for the year. “In order to match your growth in revenue,” Harmon said, “you would have to cut every other department to keep up with that.” He then said that the purpose of this meeting was to determine how the committee wants to try to fight the deficit.

The committee then had a lengthy discussion over many aspects of the budget and different funds. Board member JR Glenn asked Greeley and Harmon what few items from last year to this year increased more than others. One area they mentioned was utility costs at the John Logan building. The other they mentioned was the shelter maintenance out of the Highway Department. These bills went up quite a bit.

County Treasurer Penny Thomas mentioned insurance and how that cost was likely going to go up as well. It was mentioned that the county has several high cost claimants on the insurance.

The committee asked about grants for each department to help offset the deficit. Greeley and Harmon explained that, during their research, most of the grants that they found came with “additional projects,” meaning the department would have to undertake some project to receive that money, and it would only be for that project. Many of these grants would also not cover the entire cost, meaning the department would have to take on another expense to get that money. County Clerk Kelly Elias stated that there is a person that the department heads can go to about grants, and that her office was able to save the county about $100,000 with a grant.

[to top of second column]

 


Elias and State’s Attorney Brad Hauge spoke on their inability to make additional cuts to their department’s budget. Hauge said that his department cut $200,000 - $300,000 this year, and that he does not know where else they could cut. Elias brought out a budget from 2007 and stated that her department is running off budgeted amounts that are lower now than they were 20 years ago. Hauge also said, with the exception of the broadband project, there has not been a lot of ideas for revenue generation coming forth or being proposed.

Throughout the conversation, dipping into the county’s capital reserves was repeatedly mentioned. Greeley and Harmon stated that the county’s reserves are healthy now, but that dipping into them each year is not a viable strategy. They stated that this would only carry them for about 8 years before they ran out of funds. They also stated that cancelling projects would be their best strategy to save money, but acknowledged that these projects would likely need to be completed eventually.

Conahan then mentioned the roof of the John Logan building. The roof is in bad shape, and the Building and Grounds Committee has been trying to decide for the last couple of months if there will be enough money in the budget to get that project done next year. Several members of the Finance Committee stated that this project seemed like one that was needing to be done sooner rather than later.

Glenn then asked if it would be easier to rent spaces for their buildings rather than own them. He said that owning can be more difficult because of the additional cost that comes with fixing the spaces. Renting, however, puts the responsibility of maintenance on the landlord.

It was decided that the committee was not going to figure out how to fix the budget in that meeting, and that everyone was to take home copies of the budget and brainstorm ways to reduce it.